Evening All. If only dead tests are carried out. That would suggest Ze, Ipf, Zs and RCD tests remain outstanding. Zs can be calculated but without Ze thats not possible either. If the property is VOID, I assume on a key meter, we would need to top up the meter enough to ensure that Live tests are completed before Let. I wouldn’t accept an EICR as Satisfactory without those tests being completed.