Reply To: When should the 1st EICR be carried out after New Build?

Home Forums Main Forum When should the 1st EICR be carried out after New Build? Reply To: When should the 1st EICR be carried out after New Build?

Peter Sandry
Participant

We are striving for a 5 year cycle across the piece but would add that we currently undertake a limited number of full EICRs on new build properties when keys are handed over. Unfortunately many come back as unsatisfactory with one site submitting a number of Code 1 defects. With this in mind I wouldn’t be happy with the recommendations for 10 year from build date.